3 installing the 3tb in a borehole, 1 installing a sensor with hole lock unit – Guralp Systems CMG-3TB User Manual

Page 26

Advertising
background image

CMG-3TB

3 Installing the 3TB in a borehole

Before installing any instrument in a borehole, you should prepare the
installation site.

•

Clean the area around the borehole head, so there is clear access

all around it.

•

Keep the borehole capped at all times except when inserting or
removing the instrument, so that debris and tools do not

accidentally fall in.

•

Lay out the cables beside the borehole, or set up a cable drum
nearby, so that they do not become tangled.

•

Ensure the tripod is tall enough to hang the entire installation

(sensor and strain relief unit or digitizer) from it, with the sensor
off the ground.

•

Use a winch with a depth gauge if possible, or measure out the

cable beforehand.

Most installations are equipped with a strain relief unit, which
consists of a metal arm that swings out from the load-bearing cable to

wedge against the side of the borehole. This removes any strain in the
load-bearing cable and prevents vibrations from the surface from being

transmitted to the instrument. In installations with a downhole
digitizer, the strain relief arm is fitted to the base of the digitizer sonde;

the phrase “strain relief unit” in the following instructions should be
taken to refer to the digitizer's strain relief arm.

3.1 Installing a sensor with hole lock unit

1. Connect the signal cable to the connector on top of the sensor.

Ensure that the “O”-rings inside the housing are clean, and

tighten the knurled connector nut to its end stop.