I. INTRODUCTION

The Dual Pneumatic system is a space applied air/water
atomization system designed to introduce atomized water
into a factory setting via ON/OFF control.

II. OPERATIONAL CHARACTERISTICS

Upon a call-for-humidity, the controls will energize the

compressed air solenoid valve. An air pressure switch will

close if sufficient air pressure is present to allow for proper

atomization. When the air pressure switch contacts close,

the supply water valve opens, the water drain valve closes,

and atomization will begin. Each nozzle is equipped with

a clean-out pin that helps keep the water orifice clear of

mineral build-up each time the nozzle is cycled. Periodically,

the controls will de-energize the water control section in

order to actuate the clean-out pin to keep the water orifice

clear. During operation, if the air proving switch contacts

open, the system will de-energize. If the system ON/OFF

switch is opened the system will de-energize.

Allowable Operating Conditions

• Ambient Temperature: 40°-120°F (4°-50°C)

• Ambient Relative Humidity: 0% - 90%

• Line Voltage: -15% to +10% Nominal

• Frequency: 50/60 Hz

• Supply Air Pressure: 60-100 psig

• Supply Air Quality: Filter clean and dry to 35°F dew point.

• Supply Water Temperature: 40°-100°F (4°-38°C)

• Supply Water Pressure: 50-100 psig

• Supply Water TDS less than 50 ppm: Consult Factory

with water analysis and application data prior to selecting

equipment.

NOTE: If units are mounted in outdoor enclosures, conditions

inside enclosure must be maintained as shown above.

III. MOUNTING

The Dual Pneumatic system consists of two basic

components: the control cabinet and the atomizing-head

assemblies. The control cabinet should be mounted so that

the water outlet of the control cabinet is level or below the

water manifold. Air vents must be mounted on any loops

necessary to connect the cabinet to the manifolds.

Cabinet depth = 8.3”

Minimum Cabinet Clearances

Top: 12”, Bottom: 12”, Sides: 12”, Front: 36”

Hang the cabinet on the wall or unistrut mounting frame.

Two keyhole slots and two additional mounting holes are

provided. Be sure the unit is level and mounted directly

to the wall to wood studs as least 2” thick (or equivalent).

The atomizing head manifolds consisting of air manifolds,

atomizing heads, water manifold and unistrut brackets are to

be located as shown on specific layout drawings with each

job. Typically, a “unistrut” style mounting structure is field

fabricated to support the atomizing manifold.

Manifold Installation

1. Install the air/water manifolds per the layout drawing

included with this package.

2. Use only copper, plastic or stainless steel piping as

specified in your print package.

3. Keep runs between control cabinets and heads as short

as possible.

4. Piping runs between control cabinets and manifolds

should be as direct as possible. If loops are unavoidable,

automatic air vents must be supplied and installed.