X-unit – all components field installed – Legrand Wallduct Medical Raceway System T User Manual

Page 2

Advertising
background image

Walker Systems, Inc.
1000 Innovation Drive, Williamstown, WV 26187

©

Copyright 2000 The Wiremold Company All Rights Reserved

1 000 675 1100

X-Unit:

(Field Installation of the standard three-compartment tunnels,
bridges, and partitions.)

Installation of Tunnels and Bridges:

1. Position the tunnels in the X-unit as shown.

2. Using the holes in the tunnel flange

as a guide, drill 5/32" holes through
the bottom of the X-unit.

3. Mount the tunnels with the #10-16

x 1/4" long screws provided.

NOTE: The tunnels and bridges may be welded in place.

4. Position the bridges in the X-unit as shown.

5. Refer to steps 2 and 3 to secure the bridges.

Installation of Partitions:

1. If the partitions of the adjoining

Wallduct sections have not
been installed when the X-unit
tunnels/bridges are assembled,
cut the partitions long enough to
abut the tunnels/bridges of the X-unit.

WARNING: Gaps between partitions, tunnels, or

bridges must not exceed 1/8" [3.2mm].

2. If the partitions of the adjoining Wallduct

sections have been installed prior to the
assembly of the X-unit tunnels/bridges,
cut partition pieces from excess straight
partitions as shown on the drawing.
These pieces are required to fit between
the straight body partitions and the
tunnels/bridges of the X-unit.

X-Unit – All Components Field Installed.

Bridge

Tunnel

Partitions

Partitions

Partitions

Advertising
This manual is related to the following products: