14 Generac

®

Power Systems, Inc.

Section 3 — Operation

Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators

With the switch set to AUTO, the engine may
crank and start at any time without warning.
Such automatic starting normally occurs when
utility power source voltage drops below a pre-
set level or during the normal exercise cycle. To
prevent possible injury that might be caused by
such sudden starts, always set the switch to
OFF and remove the fuse before working on or
around the generator or transfer switch. Then,
place a “Do Not Operate” tag on the generator
panel and on the transfer switch.

3.3

AUTOMATIC TRANSFER
OPERATION

To select automatic operation, do the following:
1. Make sure the transfer switch main contacts are

set to their “Utility” position, i.e., loads connected
to the utility power source (Figure 3.2, Page 13).

2. Be sure that normal utility power source voltage

is available to transfer switch terminal lugs N1
and N2.

3. Set the generator’s Auto/Off/Manual switch to

AUTO.

4. Set the generator’s main circuit breaker to its ON

(or closed) position.

With the preceding steps complete, the generator will

start automatically when utility source voltage drops

below a preset level. After the unit starts, loads are

transferred to the standby power source. Refer to

“Sequence of Automatic Operation.”

3.4

SEQUENCE OF AUTOMATIC
OPERATION

The generator’s control panel houses a control logic

circuit board. This board constantly monitors utility

power source voltage. Should that voltage drop below

a preset level, circuit board action will signal the

engine to crank and start. After the engine starts, the

circuit board signals the transfer switch to activate

and connect load circuits to the standby power sup-

ply (load terminal lugs T1/T2 connect to terminal

lugs E1/E2).
Upon restoration of utility source voltage above a pre-

set level, generator circuit board action signals the

transfer switch to transfer loads back to that power

supply. After retransfer, the engine is signalled to shut

down.

The actual sequence of operation is controlled by
sensors and timers on a control logic circuit board,
as follows:
A. Utility Voltage Dropout Sensor

• This sensor monitors utility source voltage.
• If utility source voltage drops below about 60 per-

cent of the nominal supply voltage, the sensor
energizes a 15-second timer.

• Once the timer has expired, the engine will crank

and start.

B.Engine Warm-up Time Delay

• This mechanism lets the engine warm up for

about 10 seconds before the load is transferred
to a standby source.

C.Standby Voltage Sensor

• This sensor monitors generator AC output volt-

age. When the voltage has reached 50 percent of
the nominal rated voltage, transfer to standby
can occur.

D.Utility Voltage Pickup Sensor

• This sensor monitors utility power supply volt-

age. When that voltage is restored above 80 per-
cent of the nominal source voltage, a retransfer
time delay starts timing.

E.Retransfer Time Delay

• This timer runs for about 15 seconds.
• At end of a 15-second delay, circuit board action

de-energizes transfer relay in the transfer switch.

• Retransfer to utility power source then occurs.

F. Engine Cool-down Timer

• When the load is transferred back to utility power

source, the engine cool-down timer starts timing.

• The timer will run for about one minute, and the

generator will then shut down.

3.5

MANUAL TRANSFER OPERATION

3.5.1 TRANSFER TO GENERATOR

POWER SOURCE

To start the generator and activate the transfer switch
manually, proceed as follows:
1. Set the generator’s Auto/Off/Manual switch

to OFF.

2. Set the generator’s main circuit breaker to its

OFF (or open) position.

3. Turn OFF the utility power supply to the transfer

switch using the means provided (such as a
utility main line circuit breaker).

!