Installation Instructions

INSTALLATION—RECIRCULATING

PREPARE THE HOOD

Place the hood on a padded surface.
Position the motor housing at the back of the hood.

Electrical connectors should face the front, with
rear mounting hooks at the back.

Slip the bottom flange of the motor housing into

the side slots at the top rear opening.

Carefully lay the hood on its back.
Fasten the hood to the motor housing from the

bottom, using 6 screws.

Join two cable connectors at the front of the hood.

4

Rear

mounting

hooks

Engage flange on motor

housing into slots

Rear view

Bottom view

Rear side

Front side

To Lights

To

Control

Panel

MOUNT THE HOOD

WARNING:

2 people are required to lift and

position the hood onto the mounting bracket.

AVERTISSEMENT :

If faut deux personnes pour lever et mettre en place
la hotte sur le support de montage.

Lift the hood onto the mounting bracket.
• Position a spirit level at the bottom of the hood to

check side to side leveling.

5

LEVEL THE HOOD

This hood has built-in levelers on the mounting hooks
at each side. Use a long Phillips screwdriver from the
front to access the levelers.

Use the top screw hole in the leveler to raise or lower

the hood on that side.

Use the bottom screw hole to pull the hood tight

against the wall surface.

Mark hole location at the bottom of the hood.
Remove the hood. If the bottom screw hole does not

enter a stud, enlarge the hole to 3/8

″ and install wall

fastener anchors.

Place the hood back onto the mounting bracket,

check level again and install the wall fastener.

6

Screw hole

Levelers