PIPING

Standard Munchkin boiler
Preferred piping
(multiple boilers / zoning with circulators)

Domestic water heating mode

NOTES:

1.

This drawing is meant to show system piping concept only.
Installer is responsible for all equipment & detailing required by local codes.

2.

All closely spaced tees shall be within 4 pipe diameter center to center spacing.

3.

A minimum of 6 pipe diameters of straight pipe shall be installed upstream and downstream
of all closely spaced tees.

4.

The minimum pipe size for connecting a Super Stor water heater is 1 inch.

5.

The minimum pipe size for connecting a Munchkin boiler shall be 2.00 inches.

6.

All pumps are shown with isolation flanges. The alternative is standard flanges with full port ball valves.

7.

The anti-scald mixing valve is recommended if the DHW temperature is set above the factory setting of 119˚F.

8.

Install a minimum of 12 diameters of straight pipe upstream of all circulators.

9.

A purging valve may be used in lieu of the ball valve / hose bib combination shown.

Drawing 2F

make-up water

closely

spaced

tees

space heating zone circuit

purging

valves

Munchkin boiler

T/P

PB1

P2

Super Stor

indirect DHW tank

anti-scald

mixing valve

Munchkin boiler

T/P

PB2

zone
circulators

cold

water

Fig. 5-10