Operating procedure photos – MITSUBISHI ELECTRIC MXZ-24UV User Manual

Page 37

Advertising
background image

37

OPERATING PROCEDURE

PHOTOS

3.Removing the 4-way valve
(1)Remove the screws of the top panel , and remove it.(See

Photo 1.)

(2)Remove the service panel,rear panel,and connect cover

panel. Recover refrigerant gas.

(3)Remove the electrical parts.(See Photo 2.)
(4)Detach the brazed joint of 4-way valve and pipe.

(See Photo 4.)

4.Removing the linear expansion valve
(1)Remove the service panel.(See Photo 1.)
(Gas release is not required if the unit is pumped down.)
(2)Remove the coil of linear expansion valve.
(3)Detach the brazed joint of linear expansion valve and pipe.

4 way valve

R. V. coil

Brazing area

LEV coils

Linear
expansion
valves

Photo 4

Photo 5

2.Removing the fan motor

(1)Remove the top panel(five screws),the service panel(four

screws),and the front panel (two screws).(See Photo 1.)

(2)Disconnect the connector CN911 on the outdoor controller

board.

(3)Remove the propeller.
(4)Remove the fan motor.

OB287--2.qxp 03.1.16 10:31 AM Page 37

Advertising
This manual is related to the following products: