Installation, 6 connection to the connection modules – MGE UPS Systems 12 kVA User Manual

Page 17

Advertising
background image

51033212EN/AC

- Page 17

2. Installation

This type of connection must be carried out by qualified electrical personnel.

Before carrying out any connections, check that the battery circuit breaker is OFF
and that the upstream protection devices ( AC-power source) are open (OFF).

The overall cable diameter and the cross-sectional area
of the three wires depends on the UPS rating.

1. Remove the terminal-block cover .
2. Remove the cable entry knockouts from the cover.
3. Loosen the cable clamp .
4. Insert the cable supplying the equipment and the power cable
through the terminal-block cover .

Always connect the earthing wire first.

5. Connect the three wires of the equipment cable to the output
terminal block .
6. Connect the three wires of the power cable to the input
terminal block .
7. Tighten the cable clamp .
8. Refit and secure the terminal-block cover .

2.6 Connection to the connection modules

29

28

9

10

29

28

2

28

29

9

10

28

28

29

Earthing wires

9

10

Input terminal
block

Output terminal
block

Cable diameter

Cross-sectional area of each wire

Flexible wire

Rigid wire

Comet EXtreme
4,5 to 6 kVA

Comet EXtreme
9 to 12 kVA

15 to 25.5 mm

15 to 25.5 mm

4 to 10 mm

2

10 mm

2

4 to 16 mm

2

10 to 16 mm

2

Recommended upstream circuit
breaker

Nominal rating

(47 to 63Hz, 230V)

Maximum rating

(47 to 63Hz, 187V)

C60N 32A 2P
(maximum line
current = 26A)

C60N 40A 2P
(maximum line
current = 32A)

C60N 63A 2P
(maximum line
current = 52A)

C60N 80A 2P
(maximum line
current = 64A)

Advertising
This manual is related to the following products: