Powerware BestLink IPK-0319 User Manual

Page 28

Advertising
background image

UPS Power Management

22

BestLink SNMP/WEB Adapter User’s Guide

:

LTM-1343 B Draft 10/03/2001

3. If you entered a host name for the

Mail Server

, you must enter the IP

address of your network DNS Server in the

DNS Address

block.

4. To receive a daily status report, enter the time of day to send the

e-mail (in 24-hour format).

5. Enter the

Mail Account

,

Description

,

Mail Type

,

Event Level

, and

Event

Type

for each recipient. Refer to the online help file for more details

on each of these fields.

6. Select

Set Values

to save your changes.

Performing a Manual UPS Battery Test

You can use the BestLink Adapter to manually perform a UPS battery test. The
ability to test the UPS is model dependent, so consult your UPS
documentation for more information.

1. To manually start a battery test on a specific UPS, select

Control

from

the menu at the top of the home page.

2. Become a Superuser and then select

Initiate Battery Test

, followed by

Set Values

to start the process.

3. To stop the test while in progress, you can select

Cancel Battery Test

followed by

Set Values

.

Scheduling a UPS Battery Test

You can use the BestLink Adapter to perform a UPS battery test on a
user-defined schedule.

1. To schedule a battery test on a specific UPS, select

Control

from the

menu at the top of the home page.

2. Select

Battery Test Schedule

.

3. Become a Superuser and then select the

Test Day

and

Test Time

(in

24-hour format) for the test to be initiated by the BestLink Adapter.
The test is performed each week on the specified day and time until
the

Test Day

is changed to

Disabled

.

4. Set

Set Values

to update the adapter with the schedule information.