Assembly, Caution, Warning – Powerex Medical Packing System MPQ User Manual

Page 3: Medical package system

Advertising
background image

3

Medical Package System

compressor to avoid stresses caused
by changes in hot and cold
conditions.

3. Piping supports should be anchored

separately from the compressor to
reduce noise and vibration.

4. Never use any piping smaller than

the compressor connection.

5. Use flexible hose to connect the

outlet of the compressor to the
piping so that the vibration of the
compressor does not transfer to the
piping.

SAFETY VALVES
Tank mounted compressors are
shipped from the factory with safety
valves installed in the tank manifold.
The flow capacity of the safety valve is
equal to or greater than the capacity
of the compressor.
1. The pressure setting of the safety

valve must be no higher than the
maximum working pressure of the
tank.

2. Safety valves should be placed ahead

of any possible blockage point in the
system, i.e. shutoff valve.

3. Avoid connecting the safety valve

with any tubing or piping.

4. Manually operate the safety valve

every six months to avoid sticking or
freezing.

Assembling Modular

Medical System

MODULAR PLACEMENT

1. Unpack each module and discard all

wood shipping materials.

2. Locate frame assembly fasteners

provided in parts pack [includes:
fasteners, filter(s), isolation pads and
inlet flex line].

3. Place modules at location designated

(see picture below for proper
arrangment of modules). Provide
sufficient clearance around unit for
servicing (see minimum clearance
section).

4. Install frame assembly fasteners to

each frame joining the frames
together.

5. Lift corners of each frame assembly

and install isolation pads provided.

NOTE: Remove shipping brackets
painted orange located at the base
plate of each compressor module.
This will allow spring isolators to free
up reducing noise and vibration of
the unit.

CONNECTING PIPING

1. Locate connection for piping at rear

of unit for compressors module to
receiver tank module.

2. Remove plastic caps that protect

piping against contamination.

3. Connect flex joint to frame securely

making sure flex line is not pinched
or chinked.

4. Follow steps 1 to 3 for flex line from

dryer package to outlet of receiver
tank.

NOTE: All piping is provided and
sealed for this portion of installation.

5. Locate and attach intake inline air

filter to outside source air or header.
Flex line is provided when attaching
intake of compressors to rigid piping.

6. Connect outlet souce from filter

package located on dryer module to
outlet source piping.

Attach all inlet and
outlet source

piping in accordance with NFPA 99 for
Medical Gas.

ELECTRICAL WIRING OF MODULES

Provide electrical
power in accor-

dance to NEC and local codes. Connec-
tion of wiring should be performed by
a qualified electrician.

1. Connect wiring and flex conduit

provided from each motor junction
box to correct hole in bottom of
control panel and starter.

2. Connect each temperature switch

from the compressors to contacts
located in control panel as marked
for each temperature switch.
Temperature switches shutdown the

!

CAUTION

!

WARNING

CAL. PORT

CAL. PORT

ZERO CAL.

ZERO CAL.

ALARM

ALARM

SET

SET

ADJ.

ADJ.

PANADRY

PANADRY

F

DEW/FROST POINT

DEW/FROST POINT

PPM

PPM

AUTO CAL

AUTO CAL

CAUTION

CAUTION

ALARM

ALARM

SAFE

SAFE

FLOW

FLOW

compressor when temperature is
above 400°F.

3. Connect wiring of unload solenoids

to contacts located on control panel.
The unload solenoid provides loadless
starting of the compressors on off
cycle.

4. Connect wiring from differential

pressure switch at control panel.
Differential switch wired to contacts
in control panel provided for remote
alarm.

5. Connect wiring from CO Monitor. A

wire set is provided for power and
the other for alarm. Wiring is
marked for easy attachment.

6. Connect wiring from Dew Point

Monitor. A wire set is provided for
power and the other for alarm.
Wiring is marked for easy
attachment.

7. Dryer(s) need a separate properly

protected power supply for each
dryer. Standard voltage is 110 Volts.
Other voltages are available. Check
for voltage of dryer supplied and
current rating provided on data plate
of dryer.

NOTE: Units provided with desiccant
drying systems are wired directly to
the control panel provided.

For questions concerning assembling
and start-up, contact Powerex at 1-800-
544-0350 for technical assistance.

Operation

Powerex package medical system
operates at a maximum pressure of 100
PSIG. Compressor RPM’s are established
by Powerex based on horsepower and
operating pressure.

MPD Medical