ROUGH OPENING PREPARATION

A. Verify the opening is plumb and level.

Note: It is critical that the bottom is level.

B. Verify the door will fit the opening.

SURE

Note: 1-1/2" or more of solid wood blocking is required around the perimeter of
the opening. Fix any problems with the rough opening before proceeding.

C. Apply flashing paper at the bottom

than the width of the rough opening. Position the top edge of the flashing paper with
the top of the sill plate. Center the flashing paper with the opening width. Staple the
flashing paper to the sill plate.

Note: Sill flashing paper is not required for installation on concrete floors.

D. Apply flashing paper to the sides of the rough opening

mASHING

E. Apply bottom flashing tape #1.

WIDTH

F. Tab the bottom flashing tape and fold.

OF

'

WIDTH

In-swing Architect Series

®

and Designer Series

®

:

THIRD

Note: The flashing tape does not need to extend all the way to the interior of the framing.

(

to support the edge of the door sill. Place the sill support flush with the subfloor.

£

£

£

£









£

£



£

£