(1) NORTEC LINKS 2 START-UP CHECKLIST

WIRING

Humidifier-to-Humidifier

Connection:

Each individual humidifier linked to lead unit.

ˆ

Connection must be daisy-chained to other units.

ˆ


BMS

Network

Connection:

Lead unit wired to BMS system (Twisted Pair or Ethernet).

ˆ

Network

activity

verified.

ˆ


Controls

Wired:

Directly to humidifiers or through BMS network.

ˆ

(2) START-UP PROCEDURE

(1) Ensure power is being supplied to the humidifier, Nortec Links Module and Nortec

OnLine module. For BACnet/IP adjust network IP settings. (If this information is
provided, factory will perform necessary IP assignment).

(2) After power-up, verify network communication.

(3) Map desired network variables to BMS.

(4) Verify variable operation after mapping is complete.

(5) Perform regular humidifier start-up check.