3 wiring plan, 4 switch on phase – VEGA VEGAWELL S 51 User Manual

Page 19

Advertising
background image

Connection via VEGABOX 02
Proceed as follows:

1

Snap VEGABOX 02 onto the carrier rail or
screw it to the mounting plate

2

Loosen the cover screws and remove the
cover

3

Push the cable into VEGABOX 02 through the
cable entry

4

Loosen the screws with a screwdriver

5

Insert the wire ends into the open terminals
according to the wiring plan

6

Tighten the screws with a screwdriver

7

Check the hold of the wires in the terminals by
lightly pulling on them

8

Tighten the compression nut of the cable entry.
The seal ring must completely encircle the
cable

9

Connect the supply cable according to steps 3
to 8

10 S

crew the housing cover on

The electrical connection is finished.

4

.3

Wiring plan

Direct connection

4

1

2

2

3

Fig. 14: Wire assignment, suspension cable

1

Blue (-): to power supply or to the processing system

2

Brown (+): to power supply or to the processing system

3

Shielding

4

Breather capillaries with filter element

Connection via VEGABOX 02

1

2

+

1

2

3

4

5

6

1

2

3

4

5

6

Fig. 15: Terminal assignment VEGABOX 02

1

To power supply or the processing system

2

Shielding

3

4

.4

Switch on phase

After connecting VEGAWELL S 51 to power supply
or after a voltage recurrence, the instrument carries
out a self-check:

l

Internal check of the electronics

l

4 … 20

mA output jumps to the failure signal

The insturment delivers after this run-up period a
current of 4 … 20 mA to the cable. The value
corresponds to the actual level as well as to
settings already carried out, e.g. the factory setting.