4 Mounting

VEGAPULS 62 • 4 … 20 mA/HART - four-wire

36504-EN-121011

0%

100%

1
2
3

1

2

3

4

5

8

6

7

9

Fig. 19: Configuration surge pipe
1 Radar sensor

2 Marking of the polarisation plane

3 Thread or flange on the instrument

4 Vent hole

5 Holes

6 Weld joint

7 Welding neck flange

8 Ball valve with complete opening

9 Fastening of the surge pipe

Instructions for orientation:

Note marking of the polarisation plane on the sensor

With threaded fitting, the marking is on the hexagon, with flange

connection between the two flange holes

The marking must show to the direction of the holes in the surge

pipe

Instructions for the measurement:

The 100 % point must be below the upper vent hole and the

antenna edge

The 0 % point is the end of the surge pipe

For the parameter adjustment, select "Application standpipe" and

enter the tube diameter to compensate errors due to running time

shift

A false signal suppression with integrated sensor is recommended

but not mandatory

The measurement through a ball valve with complete run is pos-

sible