Prepare the switch. Remove and save the hex nuts

from the studs, the red arc cover, and the load base

on the expansion switch, as shown in Figure 4.

5.

Install the kit. Position the switch base over the

connecting straps, as shown in Figure 5. Replace the

load base and the hex nuts on the plate studs.

Tighten the nuts to 27–32 in-lb. turn the switch back

over to its upright position.

6.

Make the connections. Install #10-32

x

1

/

4

" screws

into the mechanism shroud mounting holes, as

shown in Figure 6. Install #10-32 screws with washers

into the straps inside the switch base and tighten to

27–32 in-lb. Invert the switch and replace the hex

nuts on the studs. Tighten the nuts to 27–32 in-lb.

7.

Install the cover. Replace the endwall barrier and

mounting screws, as shown in Figure 7. Install the

red arc cover on the switch base and tighten the

mounting screws. Position the new enclosure cover in

place on the enclosure and secure the hinge with

#10-32

x

1

/

4

" screws. Tighten the screws to 27–32 in-

lb. Reinstall the switch in the panelboard and secure

the rail latch locking screws.

Figure 4. Removng the hex nuts from the switch.

Figure 5. Installing the expansion kit.

Figure 6. Making the connections.

Figure 7. Installing the cover on the enclosure.

Load
Base

Red Arc

Cover

Hex Nuts

#10-32 x

1

/

4

"

Screw with

Washer

Enclosure

Cover