GE Industrial Solutions EntelliGuard G Carriage Position Switch Kit User Manual

Page 2

Advertising
background image

5. Slide & insert the switch assembly to engage

the cassette side sheet in the slot and push
towards the front as shown in Fig. 2

Table 3: Switch terminals for cat GCPS1R

Breaker Position

Continuity between
terminals

Disconnected D11-D14
Test D31-D34
Connected D51-D54



Table 4: Switch terminals for cat GCPS2R

Breaker Position

Continuity between
terminals

Disconnected D11-D14

&

D21-D24

Test D31-D34

&

D41-D44

Connected D51-D54

&

D61-D64

Figure 2. CPS assembly.

6. Push the complete assembly to come out side

of the cassette and the snap feature engages
with the cassette side sheet as shown in Fig.3.








Figure 3. CPS assembly

7. Ensure the assembly is firmly fitted and locked

down by the four snaps features.


8. Check functionality of carriage position switch

by racking in the breaker and racking out the
breaker and confirming changeover of switch
as specified in table 3 & 4.



9. Complete the wiring with the equipment.