Safety / installation, Equipment inspection and storage, Final equipment inspection – GE Industrial Solutions Entelli-Switch 250 User Manual

Page 3: Danger, Caution, Warning

Advertising
background image

GE Zenith Controls

3

Entelli-Switch 250 Operation and Maintenance Manual (71R-2000A)

Each GE Zenith transfer switch is factory wired and
tested. A complete information package is furnished
with each switch which includes:

a.

Sequence of operation.

b.

Description and operation of
all accessories supplied.

c.

Power panel connection diagram
and schematic.

d.

Description and identification of
all customer field connections.

Installation of GE Zenith transfer switches includes:

a.

Mounting the transfer switch cabinet.

b.

Connection of Source 1, Source 2,
and Load cables or bus bars.

c.

Connection of external control
circuits as required.

Safety / Installation

The safe operation of your switch is

GE

Zenith’s focus.

The proper storage, installation, operation and
maintenance will help increase the life of the switch.

Equipment Inspection
and Storage

Once you have received the transfer switch, inspect it
for any damage. This includes damage to the enclosure,
power panel, control panel and wiring harness. If any
damage is found or suspected, file a claim as soon as
possible with the carrier and notify the nearest

GE

Zenith representative.

Before installation, if it is necessary, store the transfer
switch in a clean dry place, protected from dirt and
water. Provide ample air circulation and heat, if neces-
sary, to prevent condensation.

5% to 95%

(non-con-

densing)

-30°C to

+75°C

(-22°F to

+167°F)

40-400

AMP

(molded shell)

-20°C to +65°C

(-4°F to +149°F)

40-4000

AMP

(all other frame

and panel types)

-20°C to +60°C

(-4°F to +140°F)

Operating

Storage

Temperature

Temperature

(Ambient):

Humidity

Final Equipment Inspection

Prior to energizing the transfer switch:

1.

Remove any debris incurred, with a vacuum,
due to shipment or installation.

2.

Verify that all cabled connections are
correct and that phase rotation of both
sources match.

3.

Check engine start connections.

4.

Verify the correct connection of all
control wires.

5.

Check settings of all timers and adjust
as necessary.

6.

Adjust any optional accessories as required.

7.

Check the lug torque values of the power
connections.

NOTE

:

Lug torque values are specified
in the power panel manual.

8.

Make sure that all covers and barriers are
installed and properly fastened.

NOTE

:

Power panels ship from GE Zenith
in Source 1 Position.

Table 1

DANGER

HAZARDOUS VOLTAGE

(Can Cause Severe Injury or Death)

Turn OFF all power before installation, adjustment, or removal of transfer switch or any of its components.

CAUTION

Due to hazardous voltage and current, GE Zenith rec-

ommends that a GE Zenith Certified technician or a

qualified electrician must perform the

installation and maintenance of the switch.

WARNING

Do not use a blower since debris may

become lodged in the electrical and

mechanical components and cause damage.

Advertising