LanPro PDU- PDU-IXXX-XXX
Installation Instructions 5/02/04
2020000502

Copyright 2003 GE Zenith Controls
All Rights Reserved
2501 Pecan Street, Bonham TX 75418
903-640-0555 Fax: 903-640-0535

battery extension cable.

17) Install the CAUTION label supplied with the PDU

assembly on the back of the LanPro UPS as shown in
Fig. 14.

18) Insure that all breakers on the PDU are in the 'ON'

position and the DC fuses have been installed.

19) Connect the 'Plug' end of the power cord, if installed, to

the appropriate U.L. Listed L6-30 or 5-50 receptacle.

20) Complete the UPS installation and start-up as outlined

in the LanPro U Installation/User manual.

21) Upon initial start-up, measure the voltage at the output

receptacles to insure proper hardware configuration
before connecting equipment to the UPS.