INSTALLATION

7

INSTALLATION

Wall drilling and bracket fixing

Wall marking:

• Draw a vertical line on the supporting wall up to the ceiling, or as high as practical, at the

centre of the area in which the hood will be installed.

• Draw a horizontal line at 450 mm above the hob.

• Place bracket

7.2.1 on the wall as shown about 1-2 mm from the ceiling or upper limit align-

ing the centre (notch) with the vertical reference line.

• Mark the wall at the centres of the holes in the bracket.

• Place bracket

7.2.1 on the wall as shown at X mm below the first bracket (X = height of the

upper chimney section supplied), aligning the centre (notch) with the vertical line.

• Mark the wall at the centres of the holes in the bracket.

• Mark a reference point as indicated at 116 mm from the vertical reference line and 590 mm

above the horizontal reference line.

• Repeat this operation on the other side.

• Drill ø 8 mm holes at all the centre points marked.

• Insert the wall plugs 11 in the holes.

• Fix the lower bracket

7.2.1 using the 12a screws (4,2 x 44,4) supplied.

• Fix the upper bracket

7.2.1 and the air outlet connection support 7.3 together using the 2

screws

12a (4,2 x 44,4) supplied.

• Insert the two screws

12a (4,2 x 44,4) supplied in the hood body fixing holes, leaving a gap of

5-6 mm between the wall and the head of the screw.

��

���

���

���

���

���

��������

�����

���