Innerduct Racking Using Jetting Equipment

The racking operation should be done before the cable has been jetted through
the Multi-Gard, unless slack is needed in vault.

1. Cut innerducts square and attach PE racking innerduct to PVC jet

terminator using coupling rated for high speed air blowing system.

2. Assemble coupling according to coupling manufacturers' recommended

instructions.

3. Rack innerduct against sides of vault at a maximum 18" radius and attach

PE innerduct to jet terminator on opposite side of vault.