DUCT PROOFING AND CABLE INSTALLATION
www.carlonsales.com
Innerduct Racking Using Jetting Equipment
The racking operation should be done before the cable has been jetted through
the Multi-Gard, unless slack is needed in vault.
1. Cut innerducts square and attach PE racking innerduct to PVC jet
terminator using coupling rated for high speed air blowing system.
2. Assemble coupling according to coupling manufacturers' recommended
instructions.
3. Rack innerduct against sides of vault at a maximum 18" radius and attach
PE innerduct to jet terminator on opposite side of vault.