PARTS AND TOOLS REQUIRED

B (1)
[Top assembly]

A (1)
[Base assembly]

H (22)
1/4-20 x 5/8"

1/4-20

G (24)
10-32 x 3/4"

E (2)
[Cross brace]

F (2)
[Alignment panel]

#2

J (18)

• 7/16"
• 13mm (use to
adjust levelers)

C (2)
[Rack rail,
left]

D (2)
[Rack rail,
right]

ASSEMBLY

NOTE:

If optional casters will be added to the base assembly,
install them now following instructions included with the
optional casters. Leave levelers installed and adjust
them using a 13mm wrench so they are as close to the
floor as possible, yet still allow movement of the rack on
the casters

.

Adding Rack Rails

1.

Place base assembly upright onto foot levelers or optional
casters.

2.

Lower one left rack rail (C) into one corner of base assembly
(A). (See Figure 1)

IMPORTANT ! : Partial install of Phillips truss head
machine screw (H) should be done BY HAND before
completing Steps 4 through 6.

3.

Partially install (by hand) one 1/4-20 x 5/8" Phillips truss
head machine screw (H) (approximately five turns) into the
base assembly (A). (See Figure 1)

Figure 1

4.

Install two 10-32 x 3/4" Phillips head screws (G) through
base assembly (A) into rack rail (C) and tighten. (See Figure 2)

5.

Tighten Phillips truss head machine screw (H) which was
partially installed in Step 3. (See Figure 2)

6.

Repeat Steps 2-5 for three remaining corners of base
assembly.

Figure 2

L

1

FR

ON

T

2

3

(H) x 1

(C)

(A)

Indicates
LEFT
rack rail

(D)

NOTE: Rack rail indicator
(L or R) must be upright
when rack rail is installed.

4

(G) x 2

5

(H) x 1

(C)

(A)

Advertising