24

excessive sound, or vibration. Follow procedures
outlined below to start each piece of equipment.
Before powering on, or starting the unit:

1. Check the unit for external damage.
2. Note all accessories installed.
3. Ensure all field and factory high and low

voltage electrical connections are correct, and
tight.

4. Check all terminal blocks, fuses, fuse blocks,

and contactors for correctness

5. Open all access panels, and remove all

shipping screws, or restraints.

6. Remove any debris that may have been left.
7. Ensure electrical supply matches the unit

nameplate.

8. Ensure condensate lines are connected and

glued.

9. Install air filters of the proper size and type.
10. Check local codes for any special provisions.
11. Replace, and/or close all access panels.
12. Ensure that return, and/or supply dampers in

ductwork are open.

13.

Check all equipment, ductwork, and piping to
verify that all work is complete, and equipment
is properly installed and mounted.

Start-Up


























DX Cooling:


1. Ensure that drain P-trap is installed.
2. Turn the unit power on.
3. Turn the unit blower on, and check for correct

rotation.

4. If correct, take blower amp readings, and

compare to see if the amp draw is within the
safety factor area of the motor.

5. Check and record ambient temperature.
6. Start the first stage cooling circuit, and blower

circuit.

7. After all stages of cooling have been on for at

least five minutes, record the return air
temperature, and supply air temperature.

8. Check the temperature difference across the

evaporator coil.

9. If equipped with an economizer, after testing

of cooling circuits is complete, turn cooling
circuits off, and leave blower running.

10. Call for the economizer circuit to operate.
11. Check for economizer blades to open fully with

no binding.

Gas Heating:

1. Ensure that gas lines have been purged of air

– wait 5 minutes after purging to allow gas to
clear before continuing with startup.

2. Turn the unit power on.
3. Turn the unit blower on, and check for correct

rotation.

4. If correct, take blower amp readings, and

compare to see if the amp draw is within the
safety factor area of the motor. Once correct,
turn blower off.

5. Check gas input and manifold pressure, and

adjust if necessary.

6. Turn on the first stage of heating.
7. Check to see that induced draft motor starts.
8. Check to see that main burner lights within 5

seconds of the heating call.

9. Ensure blower started after burner ignition.
10. Observe burner flames for light blue color, and

even flames across burner (propane flames
will have yellow tips).

11. Check temperature rise across heating section

while all stages are on.

12. If temperature rise is within range, turn all

heating calls off.

13. Check that blower stops after heat turns off





Failure to adhere to the following start-up
procedures will void all manufacturer’s warranties.

NOTE

IMPORTANT FOR 3 PHASE UNITS ONLY!


CHECK COMPRESSOR FOR PROPER
ROTATION BY STARTING UNIT ONLY AFTER
CONNECTING PRESSURE GAUGES TO
SUCTION AND DISCHARGE LINES. SCROLL
COMPRESSORS WILL BE DESTROYED IF
OPERATED IN THE WRONG DIRECTION.

CAUTION

Completed factory test sheets are in the equipment
literature packet shipped inside the unit. Factory
run-test readings recorded on the test sheets may
be helpful to reference during start-up.

NOTE