SECTION III

FIGURE 1: Typical Control Valve Station

FIGURE 2: Line Bolting Clearance

_

M ANUAL BYPASS

BLOCK

DRAIN

DRAIN

CONTROL

VALVE

BLOCK

SIG

LOA

IAS

AIRSET

I/P

PO SIT

V

2. If the pipe reducers, elbows, noise at ten u a tion

de vic es, etc., are located before and/or after
the valve body, keep these pieces as close
as practical to the valve body.

NOTES: 1. For fl angeless design, allow suf-
fi cient clear ance up stream from valve body for
line bolt in ser tion and removal. See Figure 2
and Ta ble 1.

2. Undue piping stress/strain or bending-
torques may not be transmitted through the
control valve body. One pipe (inlet or outlet)
should be anchored rigidly for piping that is
“hot” or “cold’” with respect to ambient tem-
per a ture; the remaining pipe (inlet or outlet)
should be supported and guided to ensure
uni di rec tion al expansion/con trac tion. Prop er ly
align prior to installing valve with required
fl ange bolting.

3. Clean the piping of all foreign debris, including

chips, weld scale, weld splatter, oil, grease,
sand or dirt, prior to installing the control valve.
THIS IS AN AB SO LUTE RE QUIRE MENT!

4. Field hydrostatic testing the completed pip-

ing system, including the Ranger QCT valve,
to the max allowable CWP indicated on the
valve’s name plate is acceptable. If hydro test
pres sure is to exceed this limit, the Rang er
QCT must be removed before such test ing.
Be fore pres sur iza tion, the valve plug must be
rotated out of the seat if of reverse, ATO-FC
action.

WARNING

The valve/actuator unit should not be used as a “step” to
support personnel. Failure to comply may cause leak age
at the fl ange/valve body joint, especially for fl angeless
body design.

III. INSTALLATION

A.

Orientation:

1. Preferred orientation when valve is installed

in either a horizontal or vertical pipeline is
with the valve stem horizontal. Valves may
be installed with the stem any where between
horizontal or vertical for all sizes.

2. Ranger QCT valve with actuator is not rec-

om mend ed for installation with the actuator
ori ent ed down wards.

3. In no case is additional weight to be applied

to the actuator subassembly when installed
in any orientation.

B.

Piping

System:

1. It is recommended that the control valve unit

be installed with a double-block and bypass
as indicated in Figure 1. This arrangement is
necessary when main te nance is to be done
on the valve body. Valve must be removed
from the pipeline to gain access to unit’s
internal trim parts.