SPECIFICATIONS

Table 6

and

Table 7

lists the specifications for the module.

5

POWER-UP/CHECK OUT PROCEDURE

Media Converter Modules are powered up as soon as power is applied to the chassis. The
POWER indicator (GREEN LED) on the converter module should light to indicate that VDC
power is applied to the media converter. If POWER indicator does not come on, verify that
power connections between the Media Converter Module and the power supply are secure.
Verify that there is power present at the source. If this procedure does not resolve the problem,
replace the cable or power supply.

Table 6. Electrical and Mechanical Specifications

PARAMETER

SPECIFICATION

REMARKS

Electrical

Input Voltage

+5 VDC

Backplane connector

Input power (10/100 Mb/s)

1.75 W max.

Normal operation

Input power (1000 Mb/s)

2.2 W max.

Normal operation

Mechanical

Chassis Compatibility

OptEnet Media Converter

All modular systems

Module Retention

Captive thumbscrews

Dimensions (H

×W×D)

1.14 in.

× 8.07 in.× 7.4 in.

(2.89 cm

× 20.5 cm × 18.8 cm)

Weight

0.27 lb. (122 g.)

Electrical Signal Interface

RJ45

Two twisted pair

10/100 Mb/s

RJ45

Four twisted pair

1000 Mb/s

Optical Signal Interface

LC

Singlemode 1410 – 1610 nm *

* -

Refer to the OptEnet SFP Transceiver Specifications listed in

Related Publications

, for

optical specifications.

Table 7. Module Environmental Specifications

PARAMETER

SPECIFICATION

REMARKS

Operating Conditions

41

°F to +104°F (5°C to +40°C)

Per Telcordia GR-63

Short Term Conditions +23

°F to +122°F (

5

°C to +50°C)

Per Telcordia GR-63

Storage Conditions

40

°F to +185°F (

40

°C to +85°C) at 5% to 95% RH Non-condensing

Advertising
This manual is related to the following products:

1000, 10