Installation – Poweramp SEMI AUTO TRUCK RESTRAINT 11_96 User Manual

Page 7

Advertising
background image

Installation

5

A. Blow the hole clean with compressed air, brush out

using 1" nylon brush, blow clean again. Holes
should be clean and sound. They may be dry or
damp, but should be free of standing water or frost.
Be sure rod fits into hole. If larger hole is required,
the diameter should be as close as possible to the
rod diameter.

B. Fill the hole approximately half way with adhesive

mortar starting from the rear of the hole. Slowly
withdraw the nozzle as the hole fills to avoid creating
air pockets within the hole.

C. Push the threaded rod into the hole while turning

slightly to insure positive distribution of the adhesive
mortar. Be sure rod is fully seated at the bottom of
the hole and that the mortar has flowed from the top
of the hole. If an insufficient amount of adhesive is
placed in the hole, indicated by a lack of filling to the
top of the hole when the rod is inserted, the rod must
be extracted, additional adhesive added and rod
reinserted. The threaded rod used must be free of
dirt, grease, oil or other foreign material. Allow the
adhesive mortar to cure for the time specified in chart
prior to applying any load. See Figure 10. Do not
distribute or load the anchor until it is fully cured.

Handling can be simplified and line up insured if restraint is
positioned over holes before rods are inserted for the final time.
After adhesive has cured, adjust restraint using a bubble level, so
the back is perpendicular. Shim under bottom as needed.

Install remaining six anchors using the following procedure:

Figure 7

Plumb Line

1" Main Achors

Figure 8