opening direction
12 3/4"
(32 cm)
sc40b
(x2)
sc35
(x4)
12 3/4"
(32 cm)
12 3/4"
(32 cm)
WHICH SIDE SHOULD THE
HINGES GO ON?
INSTALLING THE FENCE GATE
5
INSTALLING THE GATE HINGES
6
Open the gate
& fix the screw
2
1
Temporary base
min. 2” (5cm) high
(x3)
(x2)
s15b
18mm
s15b
18mm
X2
X2
1. The main plate of the hinge
goes on the INSIDE of the gate.
2. Once you decide which side to
put the hinges on, mark their
positions on the gate (12 3/4" / 32
cm from the top & bottom of the
gate) and install using the
supplied screw. Each hinge
requires 4 (sc35) screws on the
front plate, and 2 (sc40b) screws
on the side plate.
1. Position the assembled gate on
a temporary base (between 2”- 4” /
5-10cm high). Correct the timber
or blocks so that the gate is
horizontal and aligned with the
posts.
2. Fix the top hinge first, followed
by the bottom hinge. Mark the
position of the hinge plate holes,
and attach the hinges to the post,
using screws.