OPERATING INSTRUCTIONS DUAL SWIVEL REELS

Installation
1. The machine that you have just received is fully assembled and ready to be put into

position. Due to shipment vibration the machine should be checked to be sure all
screws and bolts are tight. Visually inspect the machine for damaged parts due to
shipment. If the machine is damaged in shipment, contact the carrier first to report
the damage, and then Rapid Air.


2. Install the machine on a level surface with sufficient clearance for loading and

unloading coils.


3. The machine is completely self-contained and need only be plugged into a 20 amp,

120 volt, 60 HZ outlet. If an extension cord is used as the source to the machine, it
should be a minimum #12 wire to keep the voltage loss down and for electrical
safety reasons.


The main control unit is located behind the side access cover. Fig. Man 14 is an illus-
tration of the layout of the control panel. This diagram lists all the components and the
approximate location of each that could be used for troubleshooting the machine if a
problem should occur. The reel can be ordered with 120 vac (1 phase) input. Termi-
nal 4 & 5 will not be used and cannot be used unless the Ramm is changed to a 220
volt controller. If using 220 vac 1 phase input wire as indicated by drawing fig. Man 14.
This unit cannot be used with 120 vac 1 phase input unless the Ramm board is
changed to a 120 volt controller.