Warning, Danger, Installation – Advanced Protection SPDee DC User Manual

Page 2: Not good good

Advertising
background image

2

Leads: Short & Straight:

Cut excess; Do not coil or loop

X

Not Good

GOOD

Cut off Excess

Length

Do Not Loop

or Coil

Short

& Straight

Figure 1

Figure 2

Sealing gasket:

two choices

1.) At 3/4" nom.

thread: ID is 1.05"

2.) At 0.14" high 'base

step': ID is 1.25"

Figure 3

INSTALLATION

Pre-Plan your installation. You need to accomplish the following:

Meet all National and Local codes (NEC

®

Art. 285 address SPDs, NEC

®

Art. 690 addresses

photovoltaic, Canadian Electric Code, Part 1)

Confirm System voltage to SPD voltage

Mount SPD as close to panel or equipment as possible to keep leads short

(long leads hurt performance substantially)

Ensure leads are as short and straight as possible, including ground. If using a breaker, use a

breaker position that is close to the SPD and the panel’s ground

If using a breaker, recommended breaker size is 30A due to 10 AWG conductor

Make sure system is grounded per NEC

®

and clear of faults before energizing SPD

(inadvertent system problem may fail SPD)

Never Hi-Pot test Any SPD (will prematurely fail SPD)

1. Ensure correct SPD; use voltmeter to check voltages as appropriate. (See Figure 1 for wire-outs).

2. Determine Mounting method (see Figure 4) – weather resistant equipment may be required.

3. Remove power from panel/source. Confirm panel/source is deenergized.

4. Identify breaker location and SPD location. Position SPD such that LED is best visible.

5. Mount SPD – weather resistant applications require additional sealing, o-rings, etc. (see Figure 3).

6. Connect conductors as appropriate - 1000V models require insulated sleeving, included

(See Figure 1 for wire-outs) – short & straight as possible (see Figure 2).

7. Label or mark conductors as appropriate (ground: green, positive: red, negative: black).

8. Make sure system is grounded per NEC

®

or CEC and is clear of hazards or faults before energizing.

9. Energize and confirm proper operation of green LED indicator. Be aware that LED requires sufficient

voltage to operate. Photovoltaic applications with low light may not generate enough power to

illuminate the LED.

V

WARNING

Do Not Hi-Pot Test

Resulting Damage is not Covered Under Warranty

DC

+

red wire

green wire

DC

-

black wire

Ground

Hazardous voltage.

Will cause death or serious injury.

Keep Out.

Qualified personnel only.

Disconnect and lock off all power

before working on this equipment.

V