Commissioning Procedure

COMMISSIONING CHECKLIST

The following should be carried out with a load on the system; otherwise the unit is likely
to short cycle. The following tests are to be carried out on 1 circuit at a time.

Switch the door interlocking MCCB to the ON position but again only on the circuit
which is to be tested

Adjust the water temperature supply and return set points to match the
system requirements

To switch the unit ON, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

Check liquid injection solenoid valve is energised and sight glass is clear

Check pressures at suction and discharge ports for correct phase rotation

CAUTION

If there is no liquid present or no differential pressure occurs, isolate immediately.

RECORD

Check the unloading solenoids operate in the correct sequence - refer to

Commissioning Data

, on page 51

Measure and record the compressor amps once the compressors are fully loaded
and then at each of the unloading stage

Measure and record full speed amps of each condenser

CAUTION

The microprocessor LP setting is adjustable via the micro display. It is
recommended that this setting be 0.6 bar below the equipment freezing point of the
cooling medium ie for water (no glycol) LP micro settings is 3.2barg.

Ensure that the low water temperature safety cuts out at the correct setting +/- 0.5°C,
to clear the alarms refer to

Alarm Handling

, on page 42

For water (no glycol) application, the recommended setting is 3°C below the design
supply water temperature (to a minimum of 3°C)

RECORD

Check the liquid line sight glass is clear and dry

Check the superheat setting adjust the expansion valve to maintain a superheat
setting of 5 - 8°C at all operating loads

Check and record the following:

Suction and discharge pressures

Liquid, discharge and suction line temperature

Water inlet and outlet temperature

Ensure the above are all within the design parameters

Repeat as follows for each circuit:

To switch the unit OFF, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

To switch the unit ON, repeat above

The unit is now commissioned and will provide many years of trouble free operation
providing the following maintenance schedule is followed.