B16c series (cop/sop) – 3-a turbine installation – Badger Meter 3-A Sanitary User Manual

Page 15

Advertising
background image

B16C SERIES (COP/SOP) – 3-A TURBINE INSTALLATION

OTEE:

N

This procedure applies to installation of replacement turbine repair kits and re-installation of cleaned or

sanitized turbine

MPORTANT

I

Before reassembly, note there are weep holes on each rotor support. These weep holes must be facing down toward the bottom of

the meter body when installed.

The meter must be reassembled with the arrowheads on the rotor pointed in the direction of fluid flow The magnetic pickup

side of the body signifies the up position This is the position that the repair kit was calibrated, and this is the position to be

used to ensure meter accuracy Due to the polished surfaces, there are no arrows on the rotor support to indicate which rotor

support is to be placed upstream or downstream Please install the repair kit as it was received in the box, using the arrow on

the rotor to determine the placement of the rotor support
1 If required by process procedures, the meter should be cleaned prior to installation into the piping system
2 Drop a thrust ball into a rotor support through the hole provided in the side Insert rotor support into the meter body

Keep the thrust bearing hole pointed upwards to keep the ball in place

3 Secure a retaining ring in the groove provided Be sure that the retaining ring is completely installed in the groove
4 Drop a thrust ball into second rotor support through the hole provided in the side Locate the rotor in the support sleeve

bearing Insert rotor support and rotor into the meter body and the first support sleeve bearing Keep the thrust bearing

hole pointed upwards to keep the ball in place

5 Secure the second retaining ring in the groove provided Be sure that the retaining ring is completely installed in

the groove

EXCESS AIR PRESSURE MAY DAMAGE THE ROTOR AND BEARINGS BY OVER-SPIN.
6 Check the meter by blowing air through the assembly If the rotor does not turn freely, the meter should be disassembled

and checked for anything that would obstruct movement of the rotor

7 Install the magnetic pickup

OTEE:

N

After installing the new repair kit, the electronics will need re-calibration Refer to the electronics’ installation and

operation manual If there are any questions on re-calibration, contact Blancett at 1 800 235 1638 or contact the

manufacturer of the associated electronics

User Manual

Page 15

November 2013

Advertising