Power verification, Verification of electrical ds3 power level, Installing the d3 – ADC DL3XR-FCA100 User Manual

Page 20: Ower, Erification

Advertising
background image

Installing a D3LX CO Module in an LEC

LTPS-UM-8013-03

12

August 30, 2002

D3LX CO and RMT Modules

Figure 7.

Installing the D3LX CO

9

After removing the protective cover from a fiber patch cord, clean the fiber-optic connector and adapter as
directed in

“Appendix B - Cleaning and Mating Fiber-Optic Systems” on page 39

.

P

OWER

V

ERIFICATION

Verification of Electrical DS3 Power Level

1

Apply power to the D3LX CO.

2

Attach the fiber patch cord from the D3LX CO to a meter.

3

Confirm that the readings are within the specification (-5 dBm to -23 dBm).

If the reading is not within the specification, check all fiber-optic connections to the D3LX CO.

If the reading is still not within the specification, replace the module.

4

Once the readings are within specification, disconnect the patch cord from the meter.

Now that the DS3 power level meets optical specifications, verify the D3LX CO module.

D3LX CO

Fiber patch cord

Fiber clip

Advertising
This manual is related to the following products: