Introduction / Installation

Page 5

When ordering parts, specify the model and serial number

of the heater. When ordering under warranty conditions,
specify the date of installation. Records of the installation
must be provided, when requested, to substantiate a claim.

Debits for defective replacement parts will not be accept-

ed and will only be replaced in kind per the manufacturer's
standard warranties.

INSTALLATION

I

NSTALLATION

C

ODES

Installations must be in accordance with local, state,

provincial, and national codes, laws, regulations and ordi-
nances. In the absence of local codes, installations must be
in accordance with the latest editions of the:

National Fuel Gas Code, ANSI Z223.1/NFPA 54

National Electrical Code, ANSI/NFPA 70

For Canada only: CAN/CGA B149.1 and .2 installation
Code (B149.1 and .2) and CSA C22.1 C.E.C. Part 1 and
Part 2

NOTE: The heater should not be located in an area
where possible water leakage will result in damage
to the area adjacent to the heater or to the structure.
When such locations cannot be avoided, it is recom-
mended that a suitable drain pan, with adequate
drainage, be installed under the heater. The pan
must not restrict combustion air flow.

C

LEARANCES

The required minimum clearances from combustible sur-

faces are shown in Table 3.

B

ASE

I

NSTALLATION

Heater must be mounted on a level base, such as

cementable slab, cement blocks or another non-combustible
surface. An alternate method for providing a base for com-
bustible floors is illustrated. Heaters may not be installed on
carpeting.

Table 3. Required Minimum Clearances from Combustible

Surfaces.

*Clearance from top of vent terminal.

When installed according to the listed minimum clear-

ances from combustible construction, the pool heater can be
serviced without removing permanent construction around
the heater.

However for ease of servicing, we recommend a clear-

ance of at least 24" in the front, and at least 18" on the rear.
This will enable the heater to be serviced in its installed loca-
tion, that is, without movement or removal of the heater.

Clearances less than these may require removal of the

heater to service either the heat exchanger or the burner tray.
In either case, the heater must be installed in a manner that
will enable the heater to be serviced without removing any
structure around the heater.

O

UTDOOR

I

NSTALLATION

NOTE: This heater is design-certified for outdoor
installation when equipped with the approved top(s)
for outdoor use.

WARNING

THE HEATER SHOULD NOT BE LOCATED IN AN AREA
WHERE WATER SPRINKLERS, OR OTHER DEVICES, MAY
CAUSE WATER TO SPRAY THROUGH THE CABINET
LOUVERS AND INTO THE HEATER. THIS COULD CAUSE
INTERNAL RUSTING OR DAMAGE ELECTRICAL COMPO-
NENTS, AND VOID THE WARRANTY.

D

IMENSIONS

CLEARANCE FROM
COMBUSTIBLE CONSTRUCTION

INDOOR INSTALLATIONS:
Top* - 42"

Back - 6"

Front - Alcove

Right Side - 6"

Vent - 6"

Left Side - 12"

OUTDOOR INSTALLATION:
Top* - Unobstructed

Right Side - 6"

Back - 6"

Left Side - 12"

Figure 3. 130A Dimensions.

ALTERNATE METHOD FOR PROVIDING A NON-COMBUSTIBLE BASE

12"

Minimum

12"

Minimum

4"

Minimum

HEA

TER

Sheet Metal

24 Gauge

Hollow concrete cinder block,
align holes and leave ends open.