1. Installation under a ventilation hood is recommended. Consult local codes.

2. Install and anchor the kettle on a level surface.

3. If the steam supply pressure is greater than the maximum working pressure

stamped on the nameplate, you must install a pressure reducing valve in the

steam supply line near the kettle.

4. Connect the steam supply line to the steam inlet fitting. Include a steam control

valve and an appropriate safety valve. To obtain the full heating capability of the

kettle, the steam supply line must be as large as the steam inlet fitting.

5. The safety valve is preset to relieve jacket pressure that exceeds its rated limit.

Do not try to adjust the valve setting, and do not allow the valve outlet or lever to

be blocked.

6. Connect the kettle condensate return line to the boiler return line, or to a drain. A

suitable steam trap, strainer, and check valve must be installed.

7. Any mechanical change must be approved by the Food Service Engineering

Department.

Floor-Mounted Models

1. Install the unit on a level surface. Ensure that there is adequate clearance at the

sides and rear, as required by the specification drawings. Anchor the pedestal or

legs securely to the floor.

2. Apply a continuous bead of clear silicone sealant (No. 732 or equivalent) to the

junction between the pedestal or leg flange and the surface, as shown in the

illustration at left. Fill all cracks and crevices, and wipe excess away.

Installation

WARNING

THIS UNIT MUST BE INSTALLED BY

PERSONNEL QUALIFIED TO WORK WITH

PLUMBING. IMPROPER INSTALLATION CAN

CAUSE INJURY TO PERSONNEL AND/OR

DAMAGE TO EQUIPMENT.

For proper sanitation, a continuous seal

is required between pedestals or flanges

and the mounting surface.