Check Charge

The 127A units may be charged in high-- or low--stage compressor
operation. Factory charge amount and desired subcooling are

shown on unit rating plate. Charging method is shown on

information plate inside unit. To properly check or adjust charge,
conditions must be favorable for subcooling charging. Favorable

conditions exist when the outdoor temperature is between 70_F
and 100_F (21.11_C and 37.78_C), and the indoor temperature is

between 70_F and 80_F (21.11_C and 26.67_C). Follow the
procedure below:
Unit is factory charged for 15ft (4.57 m) of lineset. Adjust charge

by adding or removing 0.6 oz/ft of 3/8 liquid line above or below
15ft (4.57 m) respectively.
For standard refrigerant line lengths (80 ft/24.38 m or less), allow
system to operate in cooling mode at least 15 minutes. If conditions

are favorable, check system charge by subcooling method. If any

adjustment is necessary, adjust charge slowly and allow system to
operate for 15 minutes to stabilize before declaring a properly

charged system.
If the indoor temperature is above 80_F (26.67_C), and the

outdoor temperature is in the favorable range, adjust system charge

by weight based on line length and allow the indoor temperature to
drop to 80_F (26.67_C) before attempting to check system charge

by subcooling method as described above.
If the indoor temperature is below 70_F (21.11_C), or the outdoor

temperature is not in the favorable range, adjust charge for line set
length above or below 15ft (4.57 m) only. Charge level should then

be appropriate for the system to achieve rated capacity. The charge

level could then be checked at another time when the both indoor
and outdoor temperatures are in a more favorable range.
NOTE: If line length is beyond 80 ft (24.38 m) or greater than 20
ft (6.10 m) vertical separation, See Long Line Guideline for
special charging requirements.

Final Checks

IMPORTANT: Before leaving job, be sure to do the following:

1. Ensure that all wiring is routed away from tubing and sheet

metal edges to prevent rub--through or wire pinching.

2. Ensure that all wiring and tubing is secure in unit before

adding panels and covers. Securely fasten all panels and

covers.

3. Tighten service valve stem caps to 1/12--turn past finger

tight.

4. Leave Owner’s Manual with owner. Explain system opera-

tion and periodic maintenance requirements outlined in

manual.

5. Fill out Dealer Installation Checklist and place in customer

file.

TROUBLESHOOTING

If the compressor fails to operate with a cooling call, the table
below (Resistance table) can be used to verify if there is any

damage to the compressor windings causing system malfunction.

Table 3 – Winding Resistance

Winding

Winding resistance at 70_F +/--- 20_F

(21.11_C +/--- 11.11_C)

127A024

127A036

127A048

127A060

Start

(S---C)

2.74

1.98

1.55

0.6

Run

(R---C)

0.8

0.75

0.48

0.49

Troubleshooting 127A units for proper switching

between low-- and high--stages

Check the suction pressures at the service valves. Suction pressure

should be reduced by 3--10% when switching from low to high
stage.
NOTE: The liquid pressures are very similar between low-- and
high-- stage operation, so liquid pressure should not be used for
troubleshooting.
Compressor current should increase 20 to 45% when switching

from low to high stage. The compressor solenoid when energized
in high stage, should measure 24vac. When the compressor is

operating in low stage, the 24v DC compressor solenoid coil is
de--energized. When the compressor is operating in high stage, the

24v DC solenoid coil is energized.
The solenoid plug harness that is connected to the compressor has

an internal rectifier that converts the 24v DC signal to 24v AC.
DO NOT INSTALL A PLUG WITHOUT AN INTERNAL

RECTIFIER.

Unloader Test Procedure:

The unloader is the compressor internal mechanism, controlled by

the DC solenoid, that modulates between high-- and low--stage. If
it is suspected that the unloader is not working, the following

methods may be used to verify operation:

1. Operate the system and measure compressor amperage.

Cycle the unloader on and off at 30 second plus intervals at
the thermostat (from low-- to high--stage and back to low--

stage). Wait 10 seconds after staging to high before taking a
reading. The compressor amperage should go up or down at
least 20 percent.

2. If step one does not give the expected results, remove the

solenoid plug from the compressor and, with the unit run-

ning and the Thermostat calling for high--stage, test the
voltage output at the plug with a DC voltmeter. The reading
should be 24 volts DC.

3. If the correct DC voltage is at the control circuit molded

plug, measure the compressor unloader coil resistance. The

resistance should be 32 to 60 ohms depending on com-
pressor temperature. If the coil resistance is infinite, much

lower than 32 ohms, or is grounded, the compressor must
be replaced.