Pump & Pipe
Installation Instructions

INSTALLATION B:
CONNECTION TO AN EXISTING DISCHARGE PIPE
(Diagram B)

Depending on your installation requirements,
PVC pipe lengths will vary. Cut the pipes and
assemble them as shown in photo #7. Do not
cement them together until you are sure they are
cut to the correct lengths.
It is important to
keep the discharge pipes on both pumps parallel
to each other, so that the pumps remain flat on
the floor of the sump. More detailed
instructions follow.

Unplug the main AC pump when installing the
backup pump to avoid electric shock. Failure
to do so could cause serious injury or death.

1. Cut a piece of 1½” rigid PVC pipe long enough

to reach from the bottom of the sump pit to
one (1) foot above the floor. Prime and
cement it to the 1½” pipe adapter, then screw
the adapter into the pump.

2. Install a check valve on the top of the PVC

pipe attached to the Pro Series pump. Make
sure it is installed with the arrow pointing up
or it will not prevent the backflow of water.

3. When a check valve is used, a 1/8” hole

must be drilled in the PVC pipe above the
Pro Series pump. Make sure it is above the

water line and below the check valve. Drill
the hole at a 45º angle toward the bottom
of the sump to avoid splashing water
outside the sump pit. If a 1/8” hole is not
drilled in the pipe above the pump, an air
lock may prevent the pump from operating.

4. If there is no check valve on the discharge

pipe of the main AC pump, one must be
installed at this time. Cut the discharge pipe
approximately one (1) foot above the floor.
Install a check valve on the top of the pipe
and tighten the bottom hose clamp. Now
prime and cement a small piece of 1½” PVC
pipe to the bottom of a “Y” connector. Prime
and cement the top of the “Y” assembly to the
discharge pipe with the “Y” extension facing
down toward the backup pump. Now connect
the bottom of the assembly to the check valve
and tighten the hose clamp.

5. Secure the pump wire so that the plug on the

end will not fall into the sump. Attach the
wire to the pipe with a piece of tape.

6. Place the pump with the PVC pipe attachment

on the bottom of the sump floor next to the
main AC pump. The pumps should not touch
each other.
Do not mount the pump to any
existing pipes; it should be placed on the
floor of the sump. A brick may be placed
under the pump if there are rocks or other
debris on the sump floor that may clog the
pump.

7. Connect a piece of 1½” PVC pipe above the

check valve of the Pro Series pump, and
attach a 45° elbow to that pipe. Extend
another piece of pipe to reach from the 45°
elbow to the “Y” connector on the other pipe.

8. Prime and cement all pipe connections

securely to prevent leaking, and tighten all
the hose clamps.

PUMP

WIRE

PIPE

A D APTE R

FLOOR

JO I S T

MAIN
A C PUM P

R I GI D

1-1/2"

PVC PIPE

CHECK
V A L V E

1/8" H OL E

45º ELBOW

"Y" CONNEC T O R

CHECK
V A L V E

PRO SERIES

PUMP

DRAIN TILE

SLOPE

PIPE

DOWN

Diagram B

4

5

6

7

2

3

CAUTION

!

DANGER

1