A. AC Line Connection

– Wire the

AC line input to L1 and L2 terminals
of Terminal Block TB1 as shown in
Figure 4. Be sure

both

Jumpers J1

and J2 are set to the “115V” posi-
tion for 115 Volt AC line input or to
the “230V” position for 208/230 Volt
AC line input.

B. Ground Connection

Earth

ground the control chassis using
the green ground screw that is pro-
vided on the inside of the control to
the right side of Terminal Block TB1
as shown in Figure 4.

C. Motor Connection

– Wire the

motor leads to U, V and W termi-
nals of Terminal Block TB1 as
shown in Figure 4. Be sure
Jumper J3 is set to the correspon-
ding motor horsepower rating.

D. Remote Main Speed

Potentiometer Connection

The control is supplied with a
prewired Main Speed
Potentiometer mounted on the front cover. To
operate the control from a remote potentiometer
(5kΩ), remove the white, orange, and violet
potentiometer leads from P1, P2 and P3 termi-
nals. The leads may be taped and left inside the
control.

The potentiometer assembly may be removed if a
watertight seal is used to cover the hole in the front
cover. Connect the remote main speed poten-
tiometer wires to P1 (low side), P2 (wiper) and P3
(high side) terminals as shown in Figure 5.

E. Remote Start/Stop Switch Connections

– The control is

supplied with a prewired Start/Stop switch, mounted on the
front cover. To operate the control from a remote Start/Stop
Switch (type (ON)-OFF-ON, SPDT), remove the white, black
and red wires from RUN, COM and STOP terminals. The
leads may be taped and left in the control. The switch
assembly may be removed if a watertight seal is used to
cover the hole in the front cover. Connect the remote
Start/Stop Switch wires to RUN (momentary), COM (com-
mon) and STOP (constant) terminals as shown in Figure 6.
After applying power, momentarily set the Start/Stop Switch
to the "START" position. The motor will operate at the set speed of the Main Speed
Potentiometer. To stop the motor, set the Start/Stop Switch to the "STOP" position.

6

12

Supply Wire Gauge (AWG - Cu)

Minimum

Maximum

Designation

Connection

Maximum Tightening Torque

(in-lbs)

AC Line Input

Motor

L1, L2

U, V, W

22

12

22

12

12

TABLE 3 – TERMINAL BLOCK WIRING INFORMATION

TB1

L2 AC LINE

L1

W

V

U

MOTOR

AC LINE

MOTOR

(EARTH)

GROUND

FIGURE 4 – POWER CONNECTIONS

P2

P1

P3

CON1

(BACK VIEW)

ORANGE (WIPER)

WHITE (LOW)

VIOLET (HIGH)

MAIN SPEED POTENTIOMETER

FIGURE 5 – REMOTE MAIN SPEED

POTENTIOMETER CONNECTION

RED

WHITE

BLACK

START

STOP

START/STOP SWITCH

RUN

COM

STOP

R/F

FIGURE 6 – REMOTE START/STOP

SWITCH CONNECTION

RUN

COM

R/F

STOP

FIGURE 7 – START/STOP

FUNCTION ELIMINATED