9

Ensure sufficient personnel are
on hand to lift the side (6 mini-
mum, 5 lifting, 1 placing legs.
)

• Start lifting the side using the purlins at
positions close to the legs, shifting to the
base of the upper leg to get the neces-
sary height. The purlin lifts should provide
additional vertical support at this point. See
Figure 6c.

• Insert the spliced end of the mid lower
leg into the mid upper leg. Then insert
the spliced end of the lower legs into their
respective upper legs. Pin the splices into
the upper legs.

Framelift
assemblies

Framelift
assemblies

Figure 6c

STEP 7 - Position and stake the base plates of the remaining side.

• Position one end base plate 25’-10” from the other end base plate. Measurement is from outside edge of plate to outside
edge of plate. See figure 7a.

• Then measure from this base plate diagonally to the opposite base plate. Measurement should be 39’-10” from inside cor-
ner to inside corner. See figure 7a.

• Lightly stake the plate in position.

• Position the other end base plate 25’-10” from its corresponding mate and lightly stake in place.

• Align the mid base plate between the two ends but do not stake in place. Stake only after ground bars and J bolts are
inserted into mids and base plates. (See Steps 9 to 10)

• Check and adjust until the diagonal measurements are equal.

Note: For installation of frames with
extension kits, (2) more persons and (2)
more frame lift assemblies are required
for each extension bay.

Note: For installation of frames with extension kits, use figures 7b and 7c for measurements.