BASELINE Lift BL412 User Manual

Page 12

Advertising
background image

12

17. Locate hardware to anchor posts in place. Place a nut and washer on each anchor, then

with a hammer, tap one anchor into each hole until the anchor is fully inserted and the

washer is resting on the post base. If shimming is required, leave enough thread exposed
on anchor to plumb post. After all anchors bolts have been inserted, check posts for
plumb. If adjustments are necessary, use shims to plumb posts and then tighten anchor
bolts securely.

18. Lift Adjustment: Check all cables and make sure they are all in their pulleys. Install wheel

stops and approaching ramps to runways (see diagram 5). Lubricate the inside of the posts

where contact is made with the crossbeams. Lubricate all pulleys/rollers and shafts.

19. Perform a No-Load test of the lift. Press the “UP” button to raise main platform. Press the

“UP” button to raise lift completely until it comes to a complete stop. If necessary, adjust
cables so that all four safety dogs are just above the top lock positions.

20. To lower the lift, PUSH and HOLD the Safety Release Button to disengage the safety locks,

then at the same time push DOWN on the Lowering Handle.

21. Position lift platform to a height of approximately 40" (1000mm). Using a level, verify that

the platform is level in length and width.

22. Push DOWN on the Lowering Handle to lower lift to nearest safety lock position. Verify

that all four safety locks are engaged and locked.

23. Run the lift up and down several times without load to clear air from the hydraulic system.

Installation is now complete.

Advertising