1.03 QUALITY ASSURANCE

A.

Installation: By a roofing/sheet metal contractor with at least a minimum of five years experience in similar type of
construction and documenting successful completion of contracts for projects similar in size, scope and products.

B.

Before Fabrication: The contractor shall take field measurements of the structure and substrates indicated and
specified to ensure that panel lengths and brakeformed flashings are dimensioned accurately to facilitate easy
installation. Fabrication shall not begin until all field conditions have been verified. Allow for sufficient trimming of
panel units at eaves, valleys, and gables prior to fabrication.

1.04 REFERENCES

A.

SMACNA (Sheet Metal and Air Conditioning Contractors National Association, Inc.) Architectural Sheet Metal
Manual.

B.

NRCA (The National Roofing Contractors Association) Roofing and Waterproofing Manual (including Construction
Details), and Handbook of Accepted Roofing Knowledge.

C.

Manufacturer’s Construction Details Handbook.

D.

AISC Steel Construction Manual.

E.

AISI Cold Formed Steel Design Manual.

1.05 SUBMITTALS

A.

Submit product literature, shop drawings, and samples in accordance with Section 01340.

B.

Product Literature:

1. Manufacturer’s descriptive literature.
2. Manufacturer’s standard color chart.

C.

Shop drawings are to be a small scale layout of wall plan and elevation, indicating the extent of work to be performed.
Include sections of fascia, walls, siding and soffits, for each condition, detailing flashing and trim for different
conditions, such as eaves, outside/inside corners, end wall terminations, closures, etc., showing a full and complete
installation. Show securement of panels, spacing, type and number of fasteners, as recommended by the
Manufacturer.

D.

Submit 2’0” long sample panel indicating the metal, gauge, color, texture, and finish proposed.

E.

Submit Manufacturer’s warranty covering the substrate (metal) against rupture, perforation, and structural failure due
to normal atmospheric corrosion for twenty five (25) years.

F.

Submit Manufacturer’s thirty five(35) year warranty on paint finish against cracking, peeling, blistering, chalk, and
color change.

G.

Submit test reports complying with finish specifications per section 2.05.1 through 2.05.8.

1.06 DELIVERY, STORAGE, AND HANDLING

A.

Unload and store materials at job-site to protect them from any damage.

B.

Inspect delivered material. Prevent interference by other trades or any other adverse job conditions.

C.

Store materials above ground, on skids. Protect material with waterproof covering and allow sufficient ventilation to
prevent condensation build -up or moisture entrapment in the materials.