is installed so the top of wood is flush with the top surface of the roof
insulation or recover board. The wood blocking width is to exceed the
width of flange to be attached to the blocking. The securement of the
blocking shall be in a manner to meet or exceed the local building code
requirements and the wind uplift pressure resistance required in the
project specifications.

Flex Insulation/Recover Board
Only install as much insulation or recover board as can be covered
with roofing membrane and be made watertight in the same day. Flex
Insulation/recover boards are to be installed butted together with no
gaps larger than ¼” in the joints acceptable. Gaps in the joints larger
than ¼” must be filled. Top surfaces of the insulation/recover boards
are to be aligned and flush with each other. Differences in the top
edge alignment greater than 1/8” are not acceptable.

Flex Insulation/recover board that is to be installed in multiple layers
must have the joints staggered between each layer. Flex Insulation/
recover board is mechanically attached to the roof deck with Flex
Fasteners and Flex Insulation Plates.

Restrictions
Adhesives and sealants must be protected when ambient temperatures
are lower than 40° F. Insulated, heated storage boxes must be provided
to store the products on the roof for temporary storage. Insulation and
underlayment must be stored in a manner to keep the products dry and
protected from the elements. The products must be stored off the roof
surface on skids and covered with a breathable watertight cover.