Dpa dpb : quick-start guide – Sulky VISION 1 DPB Quick set-up User Manual

Page 3

Advertising
background image

DPA DPB : Quick-start guide

MAIN menu

Shows if the hydraulic shutters
are opened or closed

Shows the electric
actuator position

g

Perform a rate calibration test

When using the buckets :
- Press on , the cursor moves to calibration test.

- Confirm by pressing , the electric actuators are

in position, from here, follow the on-screen instructions.

- Press on « start »

- Engage the DPA and drive.

- Let the fertiliser flow ( ! Max capacity of buckets)

- Weigh the collected fertiliser.

- With the numeric keypad, enter the weight and confirm with

The T-factor has been updated and you are now ready to work.

When using a weighbridge :

- If you can weigh the machine, then weigh it once

- Perform the calibration test and spread over an area (from 0.2 to X ha ), weigh the machine

again and enter the exact weight of fertiliser actually spread, confirm with

- The T-factor has been updated and you are now ready to work.

Shows the type of fertiliser

Press to operate the TRIBORD
and select the right / left or both
discs for rate modulation

Enable rate modulation

f

Set the quantity per ha

- Use the numeric keypad
- Confirm with

Réf : 400369 GB/DIS - 01