Note: Installation should be in accordance with

accepted plumbing practices. Flush all piping thor-

oughly before installation.
1. Position mixer 1

15

16

" ±

1

2

" [49mm ± 13mm] from inlet center to

finished wall surface. The tub outlet port is marked "TUB" and

should face down. Facing front of mixer, connect hot water to

left side and connect cold water to right side. The valve has

"C" and "H" cast into the body near the appropriate inlet ports.

2. Valve is factory-set for standard inlets. If reversed inlets are

required due to back-to-back installation (Cold water supply

on the left and Hot water supply on the right), follow instruc-

tions a–f below:

a. Connect cold inlet to hot port ("H") and hot inlet to cold port

("C"). Note: Do not turn valve upside down. If valve is upside

down, water will not flow properly through tub spout or

showerhead.

b. Turn water off with check stops.
c. Loosen both temperature limit screws.
d. Remove bonnet & stem
e. Turn stem 180º, making sure notch or the stem is facing

downwards.

f. While holding stem, tighten bonnet.
Note: Be certain that valve opens in full cold!
g. Hot and Cold inlets should be re-identified for reversed

inlets to avoid confusion during future maintenance.

3. For tub and shower installations (see Figure 2). Pipe bottom

outlet port "TUB" directly to the diverter tub spout. The mixer

body is designed to operate without the use of a twin ell. Pipe

top outlet port to the showerhead.

4. For shower only installation (see Figure 3) pipe top outlet port

directly to the showerhead and plug bottom port.

5. Rough-in guide installation…
a. When piping installation is completed and before doing the

finished wall, slide rough-in guide onto the mixer stem and

press fit into place (See Figure 4).

b. The rough-in guide will ensure the proper size opening for

mixer and check stop shutoff and repair accessibility, as

well as protect the chrome-plated sleeve from damage dur-

ing drywall and tile installation.

6. After wall is completed, remove rough-in guide.
7. Attach indicator plate gasket to the back of the dial plate

making sure horizontal holes match horizontal holes. Indicator

plate locator hole matches diagonal hole on the plate. Peel off

backing of dial gasket and attach to the inside top edge of the

dial plate. Gasket should be approximately 1⁄16" beyond the

plate edge.

8. Install the dial plate with the screws provided.
9. Snap on the indicator plate. Guide on the back of the plate

goes into the locator hole.

CAUTION: Indicator plate must be installed before

sleeve.
10. Install sleeve O-ring in the bonnet groove. Slide sleeve on the

bonnet.

11. Install handle and tighten the setscrew.

CAUTION:

When soldering during installation process, do not

heat the valve any higher than the temperature required to flow

solder. Excessive overheating of the valve may cause damage

to the cartridge mechanism. By following this recommendation,

you will be able to solder the valve without removing either the

cartridge or the checkstop internals. If either brazing or resis-

tance (electric) solder is to be used, all valve internals must be

removed.

Installation

n

2

Figure 2 - Rough-in Dimensions - Tub and shower

Figure 1

Cold Water Supply

Stem

Maximum

Temperature

Stop

Check Stop Assembly

Bonnet

Cartridge

Hot Water Supply

Wall

1

2

" - 14 NPT

Male Inlet

2

7

16

" (62mm) MAX.

1

7

16

" (37mm) MIN.

78" (1981mm)

Approx. to

Finished Floor

1

2

"

(13mm)

12" (305mm)

5

3

8

" (137mm)

7" (178mm)

'Tub' to be on

the bottom

4

5

8

"

(117mm)

Rough - In Guide

3

1

4

" (83mm)

5"

(127mm)

1

2

" IPS Connections or

1

2

" Copper Sweat

Connection

4" (102mm)

Balance Poppet Assembly

Mixing Plate