tekmar 132 Pump Sequencer User Manual

Page 2

Advertising
background image

©

2010 D

132

-

04/10

2

of

12

How To Use The Data Brochure

Settings ............................................................Pg 8

Testing the Control .........................................Pg 9

Error Messages ...............................................Pg 10

Technical Data .................................................Pg 12

Limited Warranty ............................................Pg 12

Sequence of Operation ..................................Pg 2

Section A: General Operation ..............Pg 2


Section B: Pump Operation ..................Pg 3


Section C: Alert Operation ...................Pg 4


Installation .......................................................Pg 5

This brochure is organized into three main sections. They are: 1) Sequence of Operation, 2) Installation, 3) Troubleshooting. The
Sequence of Operation section has three sub-sections. We recommend reading Section A: General Operation of the Sequence of
Operation
, as this contains important information on the overall operation of the control. Then read the sub-sections that apply to your
installation.

Table of Contents

Section A

General Operation

Page 2 - 3

Section B

Pump Operation

Page 3 - 4

Section C

Alert Operation

Page 4

Sequence of Operation

Section A: General Operation

POWERING UP THE CONTROL -----------------------------------------------------------------------------------------------------------------

-----------------------------------------------------------------------------------------------------------------

When the Pump Sequencer 132 is powered up, a software version code is displayed for 2 seconds, then the control turns on all
of the red LED’s for 2 seconds. After this test, the control enters its normal operating mode. When the control is powered up, the
Power light remains on continuously.

OPERATION --------------------------------------------------------------------------------------------------------------------------------------------

--------------------------------------------------------------------------------------------------------------------------------------------

The Pump Sequencer 132 has two modes of operation. The 132 is capable of operating two pumps in either a stand-by or 2-stage
configuration.

Stand-by

----------------------------------------------------------------------------------------------------------------

In the stand-by mode of operation the 132 automatically switches over from the lead pump to the stand-by pump if the lead pump
fails to provide flow in the system.

2-Stage

-----------------------------------------------------------------------------------------------------------------

In the 2-stage mode of operation the 132 turns on the second stage pump if there is a requirement for additional flow in the
system. At the same time the control still provides stand-by pump operation.

PUMP DEMAND --------------------------------------------------------------------------------------

--------------------------------------------------------------------------------------

A pump demand is required in order for the 132 to provide flow. A pump demand is gener-
ated by applying a voltage between 24 and 240 V (ac) across the Pump Demand terminals
(1 and 2). Once voltage is applied, the Pump Demand light is turned on and the pump(s)
operate as required. A pump demand can be permanently powered, or generated from an
external source such as a manual switch or another control system.

1

2

Pump

Demand

24 to 240 V (ac)