Installation

3.05 Requirements for Maximum Output

In order to obtain the maximum output capability of the

FirePower 95, a branch circuit capable of 20 amperes at

115 to 125 Volts 60 Hz is required. This generally applies

when welding steel that is equal to or greater than 12

gauge (0.105” 2.5mm) in thickness.
The rated output with this installation is 85 amperes, 18.25

Volt, 17% duty cycle (1 minute 40 seconds out of every

10 minutes used for welding).

3.06 Installing Wire Spool

As delivered from the factory, the unit is set with a 4”

(102mm) spool.
Installation of wire Spool

Assemble parts in sequence (shown in Figure 3-1 from

right to left).

1. Retaining Spring
2. "D" Washer
3. Spool
4. Locking knob (press the two tabs to remove it).

Spring

Hub

D-Ring

Wire Spool

Spool Locking
Knob

Art # A-09088

Figure 3-1: 4" Spool Installation

Advertising