After all connections have been made and before

starting up the system, ensure that all housings,

plugs, covers, etc. have been installed.

7.0 STARTUP AND OPERATION

T

O ENSURE SAFE AND RELIABLE OPERATION,

DO NOT EXCEED THE MAXIMUM OUTLET

TEMPERATURE OF 40°C AND DO NOT ALLOW

THE AIRFLOW TO DROP BELOW THE MINIMUM

AIRFLOW AS SHOWN ON THE PRODUCT

NAMEPLATE.

7.1 Turn on the airflow through the duct heater. Ensure that

the minimum airflow, as shown on the product nameplate, is

maintained at all times.

7.2 The field installed explosion-proof differential pressure switch

may require field adjustment. Consult manufacturer’s operation

instructions included with this manual.

THE PRESSURE DIFFERENTIAL SWITCH IS A CRITICAL

SAFETY COMPONENT. IMPROPER SETTING OF THE SWITCH

MAY RESULT IN HAZARDOUS CONDITIONS.

7.3 Apply power to the control panel.

7.4 Turn the control on/off switch to “On”.

7.5 Set the temperature controller to the desired set point. Do not

exceed the maximum outlet temperature of 40°C.

7.6 Ensure that the temperature controller is working properly.

Consult the manufacturer’s operation instructions supplied with the

temperature controller.

7.7 Except when purchasing a control panel to accompany your

XDF heater, the high limit set points must be set in the field. Table

2 gives the maximum high limit set points for safe operation of the

heater. For initial start-up, set the high limit controllers to the values

indicated in Table 2.

TO PREVENT UNSAFE OPERATION OF THE

HEATER, DO NOT EXCEED THE MAXIMUM

HIGH-LIMIT SET POINTS. OPERATION OF

THE HEATER WITH HIGH LIMIT SET POINTS

GREATER THAN THOSE SHOWN IN TABLE 2

CREATES A SIGNIFICANT RISK OF EXPLOSION.

Table 2 - Maximum High Limit Set Points

6.0 WIRING

Whenever hazardous materials are present,

ensure that the terminal housing covers, plugs,

etc., are secured (but not overtightened) before

energizing the heater.

All circuits must be in the open position before

removing junction or terminal box covers.

Use supply wires suitable for 90°C. Supply wires

are to be fused with appropriately sized HRC

fusing.

Use approved conduit and conduit seals as

required by hazardous location standards.

Ensure that no power is connected to the

equipment prior to making any connections.

6.1 The heater is factory prewired to supply terminal blocks in the

heater terminal housing ready for direct connection to the power

supply. The heater also contains one (1) high limit thermocouple

per heating bank that must be wired to the control equipment.

For double bank heaters, Heater Bank #1 is defined as the

inlet bank and Heater Bank #2 is defined as the outlet bank.

This distinction is important in order to ensure proper high

limit set limit set points must be set in the field. Table 2 gives

the maximum high limit set points for safe operation of the

heater. For initial start-up, set the high limit controllers to the

values indicated in Table 2.

6.2 To wire the heater to the control equipment, make the following

connections at the connection points indicated on the assembly

drawing:

a)

1¼” NPT conduit entries have been provided in each heater

terminal housing for wiring the power supply and ground to

the heaters. Connect the heating bank(s) to the contactor(s)

in the control panel.

b)

¾” NPT conduit entries have been provided on each heater

bank for wiring the J type high limit thermocouple(s) to

Certified, manual-reset high limit controller(s) in the control

panel. Using appropriate thermocouple extension wire,

connect the thermocouple(s) to the high limit controllers,

ensuring proper connection of the positive and negative

leads.

c)

Connect the “Normally Open” contacts of the supplied

pressure differential switch to the interlocks in the control

circuit.

MI289 REV.2.01 Page 3 of 4

CCI Thermal Technologies Inc. 2721 Plymouth Drive, Oakville, ON L6H 5R5 Tel. (905) 829-4422 Fax (905) 829-4430

www.ccithermal.com

Temperature Code

Heater Bank #1 (Inlet)

Heater Bank #2 (Inlet)

T2D

T3A

T3B

201 (94) 172 (78) 149 (65)

257 (125) 212 (100) 181 (83)

High Limit Set-Point °F (°C)