MOUNTING PROCEDURE

To ensure correct steering sense the unit is marked with two indents,

the unit must be installed with these forward.

The unit requires at least 65mm/2.5" clearance behind the selected

mounting position.

Use a 40mm (1 9/16th") hole cutter for the joystick body.

Ensure the gasket is fitted under the joystick body flange.

Secure in place with self-tapping screws.

Route the cable to ACP unit. Connect as per instruction in Section 4

of this handbook.


For details on how to install the controller button refer to the MOB
section.