Section 12 - Inside 90° Corner SSG Unit Glazing : B. Setting and Caulking Glazing

Figure 22

1. Set the glazing on the silicone spacer gaskets making sure glazing is pressed firmly onto the setting blocks of the temporary retainers.
2. Refer to Volume 2, pages 9 and 10 of the S-8000 Unitized Curtain Wall Assembly Instructions for assembly details and notes.
3. It is necessary to glaze one side of the corner unit, allow proper cure time, and then glaze the opposite side. Frames should not be moved until the sealant

has cured and per the sealant manufacturer’s recommendations.

4. Laying the unit flat, exterior side up, will make setting and caulking the glazing faster and with better quality control

Set glazing onto the silicone
spacer gaskets and against
the setting blocks at the
temporary glazing locators.

Note: Assembled corner units will

typically weigh in excess of 500

pounds. Proper assembly tables
and handling equipment must be

considered to facilitate safe and

speedy production methods.

HEAD

SILL