Series 8700 / 8800 Unitized Curtain Wall Assembly Instructions - Volume 4

Section 12 - Inside 90° Corner SSG Unit Glazing : B. Setting and Caulking Glazing

Figure 23

5. Remove the temporary glazing retainers
6. Apply sealant and tool the frames as required per the sealant manufacturer’s application instructions. Frames should not be moved until the sealant has

cured and per the sealant manufacturer’s recommendations.

7. Refer to Volume 2, page 9 and 10 of the S-8000 Unitized Curtain Wall Assembly Instructions for glazing instructions, details and notes.

Apply Structural

silicone

Pack sealant

into joint

HEAD

SILL

Note:
Only silicone sealants which
have been developed and tested
specifically for structural
glazing applications should be
used for glazing purposes.