If temporary glazing is required, EFCO recommends the use of (2) 12" lengths

every corner of each daylight opening resulting in 8 pieces of snap cover per

full length covers can be installed. This temporary clipping should be installed at

full length covers and the required quantity of clips have been installed.

a structural application. This system will not meet structural performances until

daylight opening. This is a temporary application only and is not to be used for

of the snap cover and (3) clips min. per cover piece, snapped in place as shown
above, at the corners of the horizontals and verticals to retain the glass until the

JDA 3/2002

& (3) ISOLATOR CLIPS PER COVER

(2) 12" COVERS w/ BULB GASKET

HORIZONTALLY & VERTICALLY

NOTE:

DUAL CLIP

9"

12"

SINGLE CLIP

TYP. TO

FIG. # 69

3"

CL

CLIP 3"

DUAL

L

C

TYP. APPLICATION SHOWING
TEMPORARY COVER
LOCATIONS

D.L.O.

TYP. TO

SINGLE CLIP

12"

6"

D.L.O.

SECTION X B - TEMPORARY

D.L.O.

USING CLIPS & COVERS

D.L.O.

GLAZING