2 installation, 1 foundation slab cure period, 2 delivery, crane rental, and assembly estimates – Rice Lake Truck Scales User Manual

Page 6: 3 recommended equipment and tools, Foundation slab cure period, Delivery, crane rental, and assembly estimates, Recommended equipment and tools

Advertising
background image

2

Survivor

®

SR Siderail Truck Scale Assembly Instrucitons

1.2

Installation

The individual components and modular sections of the SURVIVOR Siderail truck scales assemble smoothly
following a proven construction sequence. Some of the steps may change slightly depending on the lifting
equipment (crane or forklift) you have available. Assembling a single-platform gross weighing scale, or a
multi-platform axle weighing model, will require slightly different steps, but the general assembly order for all
scales will be roughly the same.

Assemble siderails and cross beams loosely on 8" setting blocks

Level and align frame to final position and tighten all bolts to final torque values

Set mounts and load cells

Install mount anchor bolts and grout beneath mount plates

Install support bars, corrugated sheet metal, and rebar for concrete deck

Pour and finish concrete deck

Install conduit, cabling, and junction boxes

1.2.1

Foundation Slab Cure Period

Standard concrete reaches full strength after a 28-day cure. Note that
the concrete foundation slab must cure in a moist state for at least
seven days (three days for high-early concrete) before driving on it. At
seven days, standard concrete is at approximately 75% of its
maximum strength and can be driven on. Driving a loaded forklift on
the slab before it reaches 75% of maximum strength may damage the
foundation.

1.2.2

Delivery, Crane Rental, and Assembly Estimates

When scheduling scale delivery and crane/forklift rental for the unloading and frame placement, arrange a full day
and a crew of at least two assemblers. A two-man crew with crane or forklift can normally unload the scale and set,
align, and bolt all components in place on the first day.*

The next day, a crew of three or four can normally prepare the scale deck for concrete, pour and finish it before
evening.*

The third day, a crew of two can grout load cell base plates, run all conduit, make electrical connections, and
connect electronic equipment.*

When the concrete deck has cured, the scale can be corner-trimmed and calibrated with test weights and
placed into service.

*

These estimated times may vary.

1.2.3

Recommended Equipment and Tools

Crane with a minimum 6,000 lb capacity, or

Forklift with 8' fork extensions

Air compressor and impact wrench with 1"
drive

3/4" rotary hammer drill

3/4" x 36" masonry carbide bit

Low-profile (8" ht.) 10-ton hydraulic jacks

8" setting blocks

Chain winches (2) with 16' chains and hooks

Torque wrench to 700 ft.lbs. with extension
handle

Box end and 1" drive socket wrenches to 1
1/2"

4' bubble level or laser level

Small torpedo level

Chalkline

100' measuring tape

25' measuring tape

Hammers and maul

Hack saw, metal snips

1 1/2" rebar chairs and metal ties

Rebar twist tie spinner tool

Concrete vibrator (for deck concrete pour)

Concrete trowels, edger, bull float, broom

Hand tools for wiring and conduit installation

Advertising
This manual is related to the following products: